  "skill_name": "risk-register",
  "evals": [
    {
      "id": 1,
      "prompt": "Build a risk register for Acme Retail's ERP migration programme for the steering group next week. Risks from the kickoff: data migration errors in product master data (owner: Data Lead, Jo Park), the systems integrator's key architect rolling off in January (owner: Programme Director, Lee Grant), cutover clashing with Black Friday trading, and finance users not trained in time (owner: Finance Systems Manager, Ravi Mehta). We use a 5x5 scale. Today is 2026-10-01.",
      "assertions": [
        "Every risk is written as a cause, an uncertain event and a consequence, not a one-word category",
        "The likelihood and impact scale is defined in the output, with what each number means and the review horizon",
        "Each risk has both an inherent and a residual score, and residual is never higher than inherent",
        "Each risk has one treatment from avoid, reduce, transfer or accept, with an action and a due date, or a named acceptor for accept",
        "The cutover risk, which has no owner in the prompt, is flagged as needing an owner rather than given an invented person's name",
        "Each open risk has a next review date and a review trigger that names an event, not just 'quarterly'",
        "The summary includes a heat map and at most five risks needing a decision, each naming the decision",
        "It does not invent controls, people or dates that are not in the prompt; any it proposes are marked as proposals or assumptions"
      ]
    }
  ]
}